![]() |
![]() |
| This 110-story steel-framed office building suffered a fire on the 11th floor on February 13, 1975. The loss was estimated at over $2,000,000. The building is one of a pair of towers, 412 m in height. The fire started at approximately 11:45 P.M. in a furnished office on the 11th floor and spread through the corridors toward the main open office area. A porter saw flames under the door and sounded the alarm. It was later that the smoke detector in the air-conditioning plenum on the 11th floor was activated. The delay was probably because the air-conditioning system was turned off at night. The building engineers placed the ventilation system in the purge mode, to blow fresh air into the core area and to draw air from all the offices on the 11th floor so as to prevent further smoke spread. The fire department on arrival found a very intense fire. It was not immediately known that the fire was spreading vertically from floor to floor through openings in the floor slab. These 300-mm x 450-mm (12-in. x 18-in.) openings in the slab provided access for telephone cables. Subsidiary fires on the 9th to the 19th floors were discovered and readily extinguished. The only occupants of the building at the time of fire were cleaning and service personnel. They were evacuated without any fatalities. However, there were 125 firemen involved in fighting this fire and 28 sustained injuries from the intense heat and smoke. The cause of the fire is unknown. |
|
Fire Commissioner John T. O'Hagan said yesterday that he would make a vigorous effort to have a sprinkler system installed in the World Trade Center towers as a consequence of the fire that burned for three hours in one of them early yesterday morning.
The towers, each 110 stories tall and the highest structures in the city, are owned and operated by the Port Authority of New York and New Jersey, which is not subject to local safety codes. As Commissioner O'Hagan stood in the sooty puddles of the North Towers's 11th floor hallway, he told reporters that the fire would not have spread as far as it did if sprinklers had been installed there. The fire spread throughout about half of the offices of the floor and ignited the insulation of telephone cables in a cable shaft that runs vertically between floors. Commissioner O'Hagan said that the absence of fire-stopper material in gaps around the telephone cables had allowed the blaze to spread to other floors within the cable shaft. Inside the shaft, it spread down to the 9th floor and up to the 16th floor, but the blaze did not escape from the shaft out into room or hallways on the other floors......... Only the 11th floor office area was burned, but extensive water damage occurred on the 9th and 10th floors, and smoke damage extended as far as the 15th floor, the spokesman said. Although there were no direct casualties, 28 of the 150 firemen called to the scene suffered minor injuries. |
|
"It was like fighting a blow torch" according to Captain Harold Kull of Engine Co. 6,........ Flames could be seen pouring out of 11th floor windows on the east side of the building. |
![]() |
![]() |
![]() | ![]() |
![]() |
![]() ![]() |
|
"On the 23rd June 1990 a fire developed in the partly completed fourteen storey building in the Broadgate development. The fire began in a large contractors hut on the first floor and smoke spread undetected throughout the building. The fire detection and sprinkler system were not yet operational out of working hours.
The fire lasted 4.5 hours including 2 hours where the fire exceeded 1000°C (1832°F). The direct fire loss was in excess of £25 million however, only a fraction of the cost (£2 million) represented structural frame and floor damage. The major damage was to the building fabric as a result of smoke. Moreover, the structural repairs after the fire took only 30 days. The structure of the building was a steel frame with composite steel deck concrete floors and was only partially (fire) protected at this stage of construction. During and after the fire, despite large deflections in the elements exposed to fire, the structure behaved well and there was no collapse of any of the columns, beams or floors. The Broadgate phase 8 fire was the first opportunity to examine the influence of fire on the structural behaviour of a modern fast track steel framed building with composite construction." |
| Building | Date | Fire Duration (hours) |
|---|---|---|
| World Trade Center North Tower | February 13, 1975 | 3 to 4 |
| World Trade Center North Tower | September 11, 2001 | 1¾ * |
| World Trade Center South Tower | September 11, 2001 | 1 * |
| World Trade Center Seven | September 11, 2001 | ** |
| 1st Interstate Bank Building | May 4-5, 1988 | 3.5 |
| Broadgate Phase 8 | June 23rd, 1990 | 4.5 |
| 1 New York Plaza Fire | August 5, 1970 | 6 |
| One Meridian Plaza | February 23-24, 1991 | 19 (11 uncontrolled) |