![]() |

| Floor | Tenant |
|---|---|
| 46-47 | Mechanical floors |
| 28-45 | Salomon Smith Barney (SSB) |
| 26-27 | Standard Chartered Bank |
| 25 | Inland Revenue Service (IRS) |
| 25 | Department of Defense (DOD) |
| 25 | Central Intelligence Agency (CIA) |
| 24 | Inland Revenue Service (IRS) |
| 23 | Office of Emergency Management (OEM) |
| 22 | Federal Home Loan Bank of New York |
| 21 | First State Management Group |
| 19-21 | ITT Hartford Insurance Group |
| 19 | National Association of Insurance Commissioners (NAIC) |
| 18 | Equal Opportunity Commission (EEOC) |
| 14-17 | Vacant |
| 13 | Provident Financial Management |
| 11-13 | Securities and Exchange Commission |
| 9-10 | US Secret Service |
| 7-8 | American Express Bank International |
| 7 | OEM generators and day tank |
| 6 | Switchgear, storage |
| 5 | Switchgear, generators, transformers |
| 4 | Upper level of 3rd floor, switchgear |
| 3 | Lobby, SSB Conference Center, rentable space, manage |
| 2 | Open to first floor lobby, transformer vault upper level, upper level switchgear |
| 1 | Lobby, loading docks, existing Con Ed transformer vaults, fuel storage, lower level switchgear |
| Storage | Pumps | Riser | Day Tank | Generators | |
|---|---|---|---|---|---|
| Office of Emergency Management | Used Silverstein to fill day tanks | Ground floor: 33.3 gpm | Located in shaft in west elevator bank | 275-gallon tank on 7th floor: one 6,000-gallon tank located between low-rise elevators in east elevator shaft between 2nd and 3rd floors | Three 500-kW on 7th floor on south side |
| Salomon Smith Barney | Two 6,000-gallon tanks under loading dock on ground level | In Fire Pump Room on ground floor: 75 gpm | Located in shaft on south west corner of building | None; pressurized recirculating loop with 2.5-inch inside diameter double wall supply and return steel pipe on 5th floor | Nine 1,725-kW on 5th floor on north side, three in south west corner |
| Silverstein Properties | Two 12,000-gallon tanks under loading dock on ground level | Between elevator shafts on west side of ground floor; 4.4 gpm | Located in shaft in west elevator bank | 275-gallon tank on 5th floor | Two 900-kW on 5th floor in south west corner |
| US Secret Service | Used Silverstein pumps | Used Silverstein pumps | Located in shaft in west elevator bank | Approximately 50-100 gallon tank under generator on the 9th floor | 9th floor |
| American Express | Day tank only | None | None | 275-gallon tank on 8th floor on west side next to exterior wall | 8th floor |
~5:20:33 p.m. WTC 7 begins to collapse. Note the two mechanical penthouses at the roof on the east and west sides in Figure 5-20.
~5:21:03 p.m. Approximately 30 seconds later, Figure 5-21 shows the east mechanical penthouse disappearing into the building. It takes a few seconds for the east penthouse to "disappear" completely.
~5:21:08 p.m. Approximately 5 seconds later, the west mechanical penthouse disappears (Figure 5-22) or sinks into WTC 7.
~5:21:09 p.m. Approximately 1 or 2 seconds after the west penthouse sinks into WTC 7, the whole building starts to collapse. A north-south "kink" or fault line develops along the eastern side as the building begins to come down at what appears to be the location of the collapse initiation (see Figures 5-23 and 5-24).
~5:21:10 p.m. WTC 7 collapses completely after burning for approximately 7 hours (Figure 5-25). The collapse appeared to initiate at the lower floors, allowing the upper portion of the structure to fall.
![]() |
![]() |
![]() |
![]() |
| 5.1 Introduction | 5-1 |
| 5.2 Structural Description | 5-3 |
| 5.2.1 Foundations | 5-3 |
| 5.2.2 Structural Framing | 5-4 |
| 5.2.3 Transfer Trusses and Girders | 5-4 |
| 5.2.4 Connections | 5-8 |
| 5.3 Fire Protection Systems | 5-10 |
| 5.3.1 Egress Systems | 5-10 |
| 5.3.2 Detection and Alarm | 5-10 |
| 5.3.3 Compartmentalization | 5-11 |
| 5.3.4 Suppression Systems | 5-12 |
| 5.3.5 Power | 5-13 |
| 5.4 Building Loads | 5-13 |
| 5.5 Timeline of Events Affecting WTC 7 on September 11, 2001 | 5-16 |
| 5.5.1 Collapse of WTC 2 | 5-16 |
| 5.5.2 Collapse of WTC 1 | 5-16 |
| 5.5.3 Fires at WTC 7 | 5-20 |
| 5.5.4 Sequence of WTC 7 Collapse | 5-23 |
| 5.6 Potential Collapse Mechanism | 5-24 |
| 5.6.1 Probable Collapse Initiation Events | 5-24 |
| 5.6.2 Probable Collapse Sequence | 5-30 |
| 5.7 Observations and Findings | 5-31 |
| 5.8 Recommendations | 5-32 |
| 5.9 References | 5-32 |
| Figure 5-1 Foundation plan - WTC 7. | 5-3 |
| Figure 5-2 Plan view of typical floor framing. | 5-4 |
| Figure 5-3 Elevations of building and core area. | 5-5 |
| Figure 5-4 Fifth floor diaphragm plan showing T-sections. | 5-6 |
| Figure 5-5 3-D diagram showing relations of trusses and transfer girders. | 5-6 |
| Figure 5-6 Seventh floor plan showing locations of transfer trusses and girders. | 5-7 |
| Figure 5-7 Truss 1 detail. | 5-8 |
| Figure 5-8 Truss 2 detail. | 5-9 |
| Figure 5-9 Truss 3 detail. | 5-10 |
| Figure 5-10 Cantilever transfer girder detail. | 5-11 |
| Figure 5-11 Compartmentalization provided by concrete floor slabs. | 5-12 |
| Figure 5-12 Sequence of debris generated by collapses of WTC 2, 1, and 7. | 5-17 |
| Figure 5-13 Pedestrian bridge. | 5-18 |
| Figure 5-14 Spread of debris around WTC 7. | 5-18 |
| Figure 5-15 Debris from the collapse of WTC 1. | 5-19 |
| Figure 5-16 Damage to the southeast corner of WTC 7. | 5-19 |
| Figure 5-17 Building damage to the southwest corner of WTC 7. | 5-20 |
| Figure 5-18 WTC 7, with a large volume of dark smoke rising from it. | 5-21 |
| Figure 5-19 Fires on the 11th and 12th floors of the east face of WTC 7. | 5-22 |
| Figure 5-20 View of WTC 7 with both mechanical penthouses intact. | 5-24 |
| Figure 5-21 East mechanical penthouse collapsed. | 5-25 |
| Figure 5-22 East and now west mechanical penthouses gone. | 5-25 |
| Figure 5-23 View from the north of the "kink" or fault developing in WTC 7. | 5-26 |
| Figure 5-24 Areas of potential transfer truss failure. | 5-27 |
| Figure 5-25 Debris cloud from collapse of WTC 7. | 5-27 |
| Figure 5-26 Debris generated after collapse of WTC 7. | 5-28 |